NOTIFICATION OF BLASTING
Description of work to be done: Drilling and Blasting on 2165 Bellamy Road.
Estimated duration of project: Starting Wednesday, April 26, 2023 until Friday, May 12, 2023.
Hours of Blasting: Monday through Friday: 8:00 a.m. to 5:00 p.m.
(No blasting, Saturdays, Sundays or Statutory Holidays)
Blasting will take place: Monday to Friday between 8:00 a.m. to 4:00 p.m., except statutory holidays. The blast locations will have proper blasting signage at all appropriate locations surrounding the sites and blasting matts will be used on each shot.
For each blast, there will be the following blast signals:
Before the blast, 12 short whistle blows at one second intervals
- A two minute pause
- Blast detonated
- A one 5 second whistle indicated the area is all clear
Contact Name: Mike Frajman, 250-619-0541
Independent Survey Company: Coast Claims Insurance Services, Craig Gamble, 250-741-6561