NOTIFICATION OF BLASTING
Description of work to be done:Â Â Â Drilling and Blasting
Estimated duration of project:    Approximately 2 (two) months, blasting will commence March 17, 2022
Hours of Blasting:                  Monday through Friday: 8:00 a.m. to 4:00 p.m.
(No blasting Saturdays, Sundays or Statutory Holidays)
The blast locations have proper blasting signage at all appropriate locations surrounding the sites.
For each blast, there will be the following blast signals:
- Before the blast, 12 blasts of a horn
- A two minute pause
- Blast will be detonated
- A long whistle indicates all is clear
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibration