About the RCMP Facility Expansion

The West Shore RCMP serves the rapidly growing communities of Langford, Colwood, View Royal, Metchosin, Highlands, Songhees First Nation, and Esquimalt First Nation. To ensure the police force can continue to serve this growing population, the municipalities are exploring options to expand the West Shore RCMP detachment.

Media Releases and Documents

Why is an expansion required?

The current detachment was constructed in the late 1990s, serving a population of approximately 47,000 people (1999 census). Since then, the West Shore region has experienced significant growth and is now home to more than 85,000 people (2021 census). This has resulted in higher demands for police services and staffing. Here are the reasons the expansion is necessary:

  • Rapid Population Growth: The population increase in the communities across the West Shore has created the need to hire additional officers, which has put a demand on the building’s capacity.
  • Space Limitations: The current facility provides 37,000 sq ft for 174 RCMP Officers, support staff, equipment, and vehicles. That number is forecasted to grow by five to seven staff each year to serve our growing population. Temporary overflow spaces have been secured, but these are short-term solutions.
  • Operational Challenges: Without expansion, the detachment cannot meet the current and future policing needs of the community effectively.

This expansion will support the RCMP to operate efficiently and continue to provide the high level of service our communities expect.

How is the facility expansion being managed?
How is the facility expansion being managed?

How is the facility expansion being managed?

The project is using an Integrated Project Delivery (IPD) model. The IPD approach brings together architects, builders, engineers, with the Owners and the RCMP in a collaborative design process. The IPD model provides for shared risk/reward and a shared governance and management structure. In this case, the IPD non-owner team members have signed the Validation Report, which commits to designing and building the project to the performance requirements, scope, and RCMP operational continuity expectations as specified, for 87.5 million. In IPD, typical cost overruns reduce the shared profit pool, which holds all consultants/contractors profits for the duration of the project and is distributed only if the project is on time and on budget. The IPD governance process is about mutual accountability for all parties signatory to the IPD contract. This results in a proactive risk mitigation focus as well as transparent and open processes where all parties work together to adapt project delivery to meet the “best for project” outcomes, not what is best for each individual company.

 

Where are we in the process?

  • Pre-Validation Phase (Complete): Initial steps included securing overflow detachment space, determining the project budget, and selecting project partners like architects and contractors.
  • Validation Phase (January 2025–Early 2026): At the January 12, 2026, Council meeting, Langford Council endorsed the West Shore RCMP Facility Expansion Validation Report.  Council Approval of the Validation Report is pending from the Town of View Royal and the City of Colwood.
  • Detailed Design (2025–2026): Finalizing the building design with input from all partners.
  • Construction (2025–2028): Demolition of portions of the detachment, site preparation, and construction an expanded detachment.
How will the facility expansion be paid for?
How will the facility expansion be paid for?

How will the facility expansion be paid for?

Borrowing to fund the proposed facility expansion is being facilitated through a partnership with the Capital Regional District (CRD). Borrowing for this project will extend over a period of 25 years.

What does this mean for the City of Langford?
What does this mean for the City of Langford?

What does this mean for the City of Langford?

As one of the funding municipalities, the City of Langford is committed to ensuring this project meets our community’s policing needs while being financially responsible. The current West Shore detachment was constructed in 1999 and has allowed for 25 years of growth. The expansion is being planned to accommodate a similar 20-25 years of growth. The project has a budget of $87.5 million plus a 25% contingency. Project funding will be managed collaboratively across the three facility owner municipalities.