Blasting: Centre Mountain Residential (Expires June 2026)
May 16, 2025
Description of work to be done: Drilling and Blasting for Langford Roadway within Centre Mountain Residential, located off Happy Valley Road
Estimated duration of project: Blasting will continue on Monday, May 19, 2025 until approximately June 2026.
Hours of Blasting: Hours of Operation Monday to Friday from 8:00 a.m. to 4:30 p.m. (No blasting on Saturdays, Sundays, or Statutory Holidays)
For each blast, there will be the following blast signals:
1. Before the blast, give 12 short whistle signals at one second intervals
2. Wait 2 minutes
3. Blast detonated
4. After area is cleared by blaster, give all clear: One ten second horn signal
5. Blasting mats will cover all blasts to safeguard persons and property
6. Seismographs will be used to monitor vibrations
Contact Name: Cole Boudreau, Colecon Contracting Ltd. – 778-268-0464
Independent Survey Company: Maple Leaf Powder Company, 250-661-3450