Blasting: 2750 Leigh Road (Expires July 2025)

June 27, 2025
Description of work to be done: Drilling and Blasting for 2750 Leigh Road
Estimated duration of project:   Commencing Tuesday, July 2, 2025 for approximately two weeks
Hours of Blasting:Â Â Â Â Â Â Â Â Â Â Â Â Hours of Operation Monday to Friday from 8:00 a.m. to 5:00 p.m.
For each blast, there will be the following blast signals:
1. Before the blast, give 12 short whistle signals at one second intervals
2. Wait 2 minutes
3. Blast detonated
4. After area is cleared by blaster, give all clear: One ten second horn signal
5. Blasting mats will cover all blasts to safeguard persons and property
6. Seismographs will be used to monitor vibrations
Contact Name:Â Tony Weaver, Surveying Specialist – Maple Leaf Powder Co. – 250-818-2337
Independent Survey Company:Â Â Acera Insurance – 250-595-5212