Blasting: 2332 Copper Rock Court (Expires June 2024)
May 10, 2024
Description of work to be done: Drilling and Blasting at 2332 Copper Rock Court
Estimated duration of  project:  Blasting will commence on Monday, May 13, 2024 and will continue for approximately 1-2 weeks
Hours of Blasting:             Hours of Operation from 8:00 a.m. to 5:00 p.m., Monday to Friday
For each blast, there will be the following blast signals:
- Before the blast, give 12 short whistle signals at one second intervals
- Wait 2 minutes
- Blast detonated
- After area is cleared by blaster, give all clear: One ten second horn signal
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibrations
Contact Name:Â Matt Flock – 250-415-3343
Independent Survey Company: Hendry, Swinton, McKenzie Insurance Services Inc. – 250-388-5555