Blasting: 2627 - 2631 Millstream Road (Expires March 2023)
January 17, 2023
Description of work to be done: Blasting at 2627 – 2631 Millstream Road
Estimated duration of project: Commencing Monday, January 23, 2023 for approximately 2 months
Hours of Blasting: Hours of Operation from 8:00 a.m. to 4:30 p.m, Monday to Friday.
For each blast, there will be the following blast signals:
- Before the blast, give 12 short whistle signals at one second intervals
- Wait 2 minutes
- Blast detonated
- After area is cleared by blaster, give all clear: One ten second horn signal
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibrations
City of Langford: 250-478-7882
Contact Name: Dave Purnell at 250-727-1752 – dave.purnell@hhsdrillingandblasting.com
Independent Survey Company: Hendry Swinton McKenzie Insurance Services Inc. 250-388-5555