Blasting: 2681 & 2689 Leigh Road (Expires March 2024)
March 03, 2023
Description of work to be done:  Blasting at 2681 & 2689 Leigh Road
Estimated duration of  project:   Commencing Monday, March 06, 2023 for approximately 12 months
Hours of Blasting:                Hours of Operation from 8:00 a.m. to 5:00 p.m, Monday to Friday, except statutory holidays.
For each blast, there will be the following blast signals:
- Before the blast, give 12 short whistle signals at one second intervals
- Wait 2 minutes
- Blast detonated
- After area is cleared by blaster, give all clear: One five second horn signal
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibrations
City of Langford:Â 250-478-7882
Contact Name:Â Chris Conley at 250-365-9833 – littlerockdrilling2020@shaw.ca
Independent Survey Company:Â Â Kootenay Insurance Services Ltd. (250)368-9174