Blasting: 2929 Sooke Road (Expires December 2023)
May 31, 2023
Description of work to be done: Blasting at 2929 Sooke Road
Estimated duration of project: Commencing Friday, June 09, 2023 for approximately 6 months
Hours of Blasting: Hours of Operation from 8:00 a.m. to 4:30 p.m, Monday to Friday.
For each blast, there will be the following blast signals:
- Before the blast, give 12 short whistle signals at one second intervals
- Followed by a 20 second pause
- Blast will be detonated
- After area is cleared by blaster, give all clear: One ten second horn signal
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibrations
Contact Name: Dave Purnell at 250-727-1752 –
Independent Survey Company: Hendry Swinton McKenzie Insurance Services Inc. 250-388-5555