Blasting: Centre Mountain Business Park (Sooke Road) (Expires July 2024)
January 16, 2024
Description of work to be done: Drilling and Blasting for Langford Roadway within the Centre Mountain Business Park, located off Sooke Road.
Estimated duration of project:   Commencing 3rd week of January, 2024 for approximately 6-7 (six to seven) months.
Hours of Blasting:                Hours of Operation Monday to Friday from 8:00 a.m. to 5:00 p.m.
For each blast, there will be the following blast signals:
1. Before the blast, give 12 short whistle signals at one second intervals
2. Wait 2 minutes
3. Blast detonated
4. After area is cleared by blaster, give all clear: One ten second horn signal
5. Blasting mats will cover all blasts to safeguard persons and property
6. Seismographs will be used to monitor vibrations
Contact Name: Matt Floch – 250-415-3343
Independent Survey Company:Â HSM Insurance Westshore Branch – 250-478-5588