Read All Advisories
Blasting: Langford Heights - Millstream Road (Expires October 2024)
June 26, 2024
Description of work to be done: Drilling and Blasting at Langford Heights Development
Estimated duration of  project:  Blasting will be commencing and continuing through until approximately September 30, 2024
Hours of Blasting:             Hours of Operation from 8:30 a.m. to 5:00 p.m., Monday to Friday
For each blast, there will be the following blast signals:
- Before the blast, give 12 short whistle signals at one second intervals
- Wait 2 minutes
- Blast detonated
- After area is cleared by blaster, give all clear: One ten second horn signal
- Blasting mats will cover all blasts
- Seismographs will be used to monitor vibrations
Contact:Â or contact Worksafe BC
Independent Survey Company:Â HUB International Insurance Brokers – 250-765-4143