Blasting: Myles Mansell Road (Expires August, 2022)
Â
February 10, 2022
NOTIFICATION OF Â BLASTING
Â
Description of work to be done: Blasting rock formations for service trenches and footings
Estimated duration of project: Approximately 6 (six) months
Hours of Blasting:             Monday through Thursday: 8:30a.m. to 4:00 p.m.
Friday: 8:30 am to 3:00 pm
(No blasting, Sundays or Statutory Holidays)
The blast locations have proper blasting signage at all appropriate locations surrounding the sites.
For each blast, there will be the following blast signals:
- Before the blast, 12 blasts of a horn
- A two minute pause
- Blast detonated
- A 15 second blast indicating the area is now safe
City of Langford:Â 250-478 -7882
Contact Name: Chris Conley 250-365-9833
Independent Survey Company : Kootenay Insurance Services Ltd 250-426-6657